A scheduled data center migration will take place on 25th February 2023 starting at 22:00 CET, with impacts on the following services.

The primary site will be moved from Senigallia to Milan, and Senigallia will become the disaster recovery site.

In order to complete migration we will expose the services on a new proprietary subnet.

The changement of IP addresses may impact your services if you have whitelisted IPs or similar activities. It will be necessary to add the pointing to the IPs currently in use with new pre-established IPs without removing the existing. 

In this case you should in alternative:


IP mapped

new IP to be added

185.217.30.119

185.217.29.20

185.217.30.118

185.217.29.19

185.217.30.126

185.217.29.18

185.217.30.125

185.217.29.17

185.217.30.121

185.217.29.16

185.217.30.122

185.217.29.15

185.217.30.120

185.217.29.14

185.217.30.117

185.217.29.13

185.217.30.116

185.217.29.12

185.217.30.115

185.217.29.11


Here are the services that will be affected by the system operation.

Legend:

Stop: If the service is affected by the 4h downtime starting at 10.00 pm on February 25th, 2023.

Change IP: If the service requires a change of the IP configuration if it is whitelisted.

Services Migration Data Center: If the service is migrated to the new Milan infrastructure.